Main Contractor – Balfour Beatty
This was the follow on project from phase 1. This phase is still ongoing, phase 2 is mainly made up of the new Treated Water Tank. The tank is 50m x 40m and 6m tall. The tank has a 450mm thick wall around the perimeter and 50+ radius columns throughout the tank to support the soffit that we are supporting 6m in the air.